Resource Limitation/Restriction in Primavera

7 replies [Last post]
Irfan Khan
User offline. Last seen 10 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

3600
example.jpg

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

this depends on your logic if Activity A, B & C have Start to Start relationship with one crew and Activity D, E & F have Start to Start relationship with the same crew thne make activity D a successor to activity A and make E a successor to activity B and make activity F a successor to activity C or make D a successor to activity A all with FS relationships.

wang chao
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 21 Mar 2011
Posts: 7

Actually it is the workflow function, I think this is can't automatic generate (depending on the current reviosn function) .It only can be found by manual.

Raymund de Laza
User offline. Last seen 35 weeks 21 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

After Setting my suggestions... run Resource Levelling with priorities.

Hope this will help.

Irfan Khan
User offline. Last seen 10 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Thaks Mr. Raymund for your reply,

 

Settting MAX Unit/Time is not solving my problem, let me explain you again that :

I have only one crew which is working parellay with 1st group of activities i.e. activity A, B & C, second part is that my activties D, E & F will start just completion of activity A, B & C. 

 

all activities has assigned one crew only which will work only when my Group 1 Activities will finish, therefore i am wondering an option whcihc will stop me to start any activity in group to unless all of actvities finish in Group 1.

 

Hope you understand what i am looking for.

 

thanks.....

Raymund de Laza
User offline. Last seen 35 weeks 21 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Set the MAX Unit/Time for the Crew in the resource Pane. In your example the MAX unit is 3 Multiplied by Working Time for the crew per day. Say your crew will work 8hrs per day then your MAX will be 24hrs/day.

Hope this will help

Irfan Khan
User offline. Last seen 10 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Hi to all Experts,

 

I was wondering that how to manage my limited resources through Primavera P6.

 

If the Case is like that :

 

I have 6 activities 

Activity A

Activity B

Activity C

Activity D

Activity E

Activity F

Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship. 

the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.

hence, i want restriction on activities with the help of due to limited resource.

Hope i everything is clear here, for more information please see the snap shot.

thanks...... :)

 

 

 

 

Irfan Khan
User offline. Last seen 10 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Hi to all Experts,

 

I was wondering that how to manage my limited resources through Primavera P6.

 

If the Case is like that :

 

I have 6 activities 

Activity A

Activity B

Activity C

Activity D

Activity E

Activity F

Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship. 

the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.

hence, i want restriction on activities with the help of due to limited resource.

Hope i everything is clear here, for more information please see the snap shot.

thanks...... :)