PMSDK.ini file missing error during SDK setup

4 replies [Last post]
zyoxizol Gajjar
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 21 Apr 2015
Posts: 4
Groups: None

Hi,

Anyone who is using P6 SDK successfully should be able to help with my error. I am using 32-bit P6 v7 with 32-bit ODBC data source and 32-bit excel. For some reason I can't get SDK to work.

My error: 

Row 0: RDA error: Resource not available - Connect error: da=PMSDK;Driver=PMSDK;engine=PM;lf=C:\temp\PMSDK.LOG;lo=terse;pg=1;pp=pubuser;pu=pubuser;. Error returned from engine: VDB.Connect; Exception=TCIniFile.Create: Unable to locate .ini file, C:\WINDOWS\PMSDK.ini Error number: 0x80004005

 

I will appreciate if I get solution to the issue or at least PMSDK.ini file from someone. File is usually located here C:\Windows

Thanks

Z

Replies

Zoltan Palffy
User offline. Last seen 15 weeks 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

here you go 

 

[Application] SubSuite=E AppType=orion Suite=P3E LastUserName=admin CommonPath=   ApplicationType=ERPM SuiteType=P3E [CustomConfiguration] appoptionspath=C:\Program Files (x86)\Common Files\Primavera Common\ configfile=   configpath=C:\Program Files (x86)\Common Files\Primavera Common\ appoptions=SuiteInfo2.xml
zyoxizol Gajjar
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 21 Apr 2015
Posts: 4
Groups: None

Hi Zoltan,

Appreciate your reply.

I checked my C:\Program Files (x86)\Common Files\Primavera Common\PMSDK\Engines but can't find any .INI files there as well as nothing under C:\Windows.

The only reason I thought file was under C:\Windows because I got this error which logged that file was missing from that location.

“”Row 0: RDA error: Resource not available - Connect error: da=PMSDK;Driver=PMSDK;engine=PM;lf=C:\temp\PMSDK.LOG;lo=terse;pg=1;pp=privuser;pu=privuser;.

Error returned from engine: VDB.Connect; Exception=TCIniFile.Create: Unable to locate .ini file, C:\WINDOWS\PMSDK.ini

Error number: 0x80004005”

Anyway, is there any chance of getting my hands on your PMSDK.INI file or what is written in it? It will be a great help if you can post what is written in it as .INI files are only text document (need admin access though).

Thanks again Zoltan (the original Z :) )

Regards,

Z

zyoxizol Gajjar
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 21 Apr 2015
Posts: 4
Groups: None

Hi Zoltan,

Appreciate your reply.

I checked my C:\Program Files (x86)\Common Files\Primavera Common\PMSDK\Engines but can't find any .INI files there as well as nothing under C:\Windows.

The only reason I thought file was under C:\Windows because I got this error which logged that file was missing from that location.

“”Row 0: RDA error: Resource not available - Connect error: da=PMSDK;Driver=PMSDK;engine=PM;lf=C:\temp\PMSDK.LOG;lo=terse;pg=1;pp=privuser;pu=privuser;.

Error returned from engine: VDB.Connect; Exception=TCIniFile.Create: Unable to locate .ini file, C:\WINDOWS\PMSDK.ini

Error number: 0x80004005”

Anyway, is there any chance of getting my hands on your PMSDK.INI file or what is written in it? It will be a great help if you can post what is written in it as .INI files are only text document (need admin access though).

Thanks again Zoltan (the original Z :) )

Regards,

Z

Zoltan Palffy
User offline. Last seen 15 weeks 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

The default location of the SDK INI file is C:\Program Files\Common Files\Primavera Common\PMSDK\Engines\PMSDK.INI

However mine is located in C:\Program Files (x86)\Common Files\Primavera Common\PMSDK\Engines

NOT C:\Windows 

 

Thanks

The Original "Z"