Resource Price/Unit Changes & Baseline Values

1 reply [Last post]
Marc Timberlake
User offline. Last seen 3 years 13 weeks ago. Offline
Joined: 18 Mar 2015
Posts: 9
Groups: None

Hi,

Hopefully someone here will be able to help.

I'm working on a project with a baseline that matches the approved client changes for reporting purposes. We are just about to apply new hourly rates to our labour resources (new rates from effective date). Will this automatically update the resources on the baseline? Ideally we want all values in the baseline to remain the same until such time that the uplifted rates are approved via change.

any help much appreciated.

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

not it wil not update the baseline the setting that were in effect when the resources were added remain ineffect. ALL of the rates in the baseline will rmain the SAME.

If the baseline is assigned what you can do is select update baseline and check

Update Existing activites already in the baseline

then check When updating resource assignments data, include:

and then check Update existing resources and role assignments 

and then check Budgeted Units and cost