Hi,
Hopefully someone here will be able to help.
I'm working on a project with a baseline that matches the approved client changes for reporting purposes. We are just about to apply new hourly rates to our labour resources (new rates from effective date). Will this automatically update the resources on the baseline? Ideally we want all values in the baseline to remain the same until such time that the uplifted rates are approved via change.
any help much appreciated.