How to clear the "Unsatisfied Relationship" in schedule log?

2 replies [Last post]
Richard Chen
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 2 Jan 2015
Posts: 4
Groups: None

Hi all:

 

I am a planner from Taiwan, and in a Sabic project by now.

The client requested me to clear all the Unsatisfied Relationship in schedule log.

I tried many times by still can't find a logical way to clear it all.

THANKS FOR YOUR KINDLY HELP~

 

1. What is the definition of "Unsatisfied Relationship"?

2. How to clear it in schedule log?

Replies

Richard Chen
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 2 Jan 2015
Posts: 4
Groups: None

Thanks Gong,

I cleared some "unsatisfied relationship" by your way.

 

I found that A is predecessor and B is successor, A connects to B with FF relationship.

IF B has a actual start, the FF relationship will be defined as "unsatisfied relationship".

Only I can do is to remove the relationship or change the relationship to SS.

Yanqing Gong
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 20 Mar 2012
Posts: 10

Hi, Chen,

I also encountered this problem, and found that when I remove the "SS" relationship linked to the completed activity, the corresponding "Unsatisfied Relationship in schedule log" would disappear. You can have a try.Hope this can help you.