Error exporting xml in P6 R8.2 Standalone

5 replies [Last post]
James Reece
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 11 Jan 2015
Posts: 4
Groups: None

Hi all, 

I very much need to be able to export schedules in xml format but when I try I receive the following error:

Export Failed. See file log for details. 

Can anybody help me to enable xml exports, or explain to me what the problem is? Thanks in advance, any help would be very much appreciated. 

Here is the logfile output. 

com.primavera.integration.client.ClientException: Fatal error: null

at com.primavera.integration.client.Session.a(Session.java:379)at com.primavera.integration.client.Session.login(Session.java:339)at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172)at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33)Original Exception:java.lang.NullPointerExceptionat com.primavera.bo.datacaches.ServerUserPrivsCache.getServerUserPrivsCache(ServerUserPrivsCache.java:765)at com.primavera.bo.common.b.a(LoginHelper.java:360)at com.primavera.bo.common.b.a(LoginHelper.java:166)at com.primavera.bo.remotable.SessionLifetime.login(SessionLifetime.java:57)at com.primavera.bo.remotable.qproxy.SessionLifetime.login(SessionLifetime.java:76)at com.primavera.bo.DBSessionLifetime.login(DBSessionLifetime.java:26)at com.primavera.integration.server.ServerFacadeBase.login(ServerFacadeBase.java:411)at com.primavera.integration.server.ServerFacade.login(ServerFacade.java:11)at com.primavera.integration.client.LocalSession.login(LocalSession.java:92)at sun.reflect.NativeMethodAccessorImpl.invoke0(Native Method)at sun.reflect.NativeMethodAccessorImpl.invoke(NativeMethodAccessorImpl.java:62)at sun.reflect.DelegatingMethodAccessorImpl.invoke(DelegatingMethodAccessorImpl.java:43)at java.lang.reflect.Method.invoke(Method.java:483)at com.primavera.integration.client.Session.a(Session.java:351)at com.primavera.integration.client.Session.login(Session.java:339)at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172)at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33)

Replies

LOKESH KONGANAPALLE
User offline. Last seen 9 years 1 week ago. Offline
Joined: 9 Dec 2015
Posts: 2
Groups: None

Hello Kindly help me on the error

 

com.primavera.integration.client.ClientException: Fatal error: null

at com.primavera.integration.client.Session.a(Session.java:379)

at com.primavera.integration.client.Session.login(Session.java:339)at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172)at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33)Original Exception:java.lang.NullPointerExceptionat com.primavera.bo.datacaches.ServerUserPrivsCache.getServerUserPrivsCache(ServerUserPrivsCache.java:765)at com.primavera.bo.common.b.a(LoginHelper.java:360)at com.primavera.bo.common.b.a(LoginHelper.java:166)at com.primavera.bo.remotable.SessionLifetime.login(SessionLifetime.java:57)at com.primavera.bo.remotable.qproxy.SessionLifetime.login(SessionLifetime.java:76)at com.primavera.bo.DBSessionLifetime.login(DBSessionLifetime.java:26)at com.primavera.integration.server.ServerFacadeBase.login(ServerFacadeBase.java:411)at com.primavera.integration.server.ServerFacade.login(ServerFacade.java:11)at com.primavera.integration.client.LocalSession.login(LocalSession.java:92)at sun.reflect.NativeMethodAccessorImpl.invoke0(Native Method)at sun.reflect.NativeMethodAccessorImpl.invoke(Unknown Source)at sun.reflect.DelegatingMethodAccessorImpl.invoke(Unknown Source)at java.lang.reflect.Method.invoke(Unknown Source)at com.primavera.integration.client.Session.a(Session.java:351)at com.primavera.integration.client.Session.login(Session.java:339)at com.primavera.integration.app.importexport.ImportExportAction.b(ImportExportAction.java:172)at com.primavera.integration.app.importexport.ImportExportMain.main(ImportExportMain.java:33)
Zoltan Palffy
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

glad I could help

James Reece
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 11 Jan 2015
Posts: 4
Groups: None

It worked!    Thank you very much Zoltan!

James Reece
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 11 Jan 2015
Posts: 4
Groups: None

It worked!    Thank you very much Zoltan!

Zoltan Palffy
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

This issue is caused by using an unsupported Java JRE version (1.8.x)

To solve this issue

 

1) Uninstall the actual Java 1.8.0_X from the machine. 

2) Install a Java version that appear in the tested configuration list for your P6 version Primavera Official Documentation >

Select your P6 version > click on "Tested Configurations" > select the tab Client.

3) Configure the JAVA_HOME to point to this new java environment following 

4) Reboot machine.