Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

FF Relationship with minus lag

6 replies [Last post]
Jason LI
User offline. Last seen 3 years 39 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

Dears,

When you are using FF relationship, Do you use the minus Lag or not, like Activity B FF after Activity A Minus 10 days, if using minus log, will it working correct or not?

Thanks for your reply

Jason

Replies

Hi Jason,

we do not advise to use negative lags but FF relationships are not rare in construction, especially in linear projects like road, pipeline and similar objects construction. Usually FF is used together with SS link (plus lag) with the same activities. These links usually reflect the requirement to keep certain distance between the crews that are doing consequent works.

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jason

Because software developers have never worked in construction.

SS - FF links do have a place in manufacturing on a production line where a "ladder" system works well.

Early MSP systems blocked FF links but they changed it in the latest versions.

Best regards

Mike Testro

Zoltan Palffy
User offline. Last seen 3 days 1 hour ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

agree never use a negative lag. A lot of time scheduling specifications prohibits the use of negative lags. 

Jerome Odeh
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 19 Jan 2004
Posts: 102

Hi Jason,

 

Like Mike said, never use FF relationships in a construction, installation or a working schedule. FS is the way to go.

I'll only recommend use of FF & SS relationships when building a high-level schedule for

  1. Management reporting
  2. Integrating different contractors schedule
Jason LI
User offline. Last seen 3 years 39 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

Thanks Mike,

If only think it from the soft wise, and not consider the construction step, why P6 Provide the FF relation, and when we can use the FF relation actually.

 

Best regards,

Jason.

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jason

Never ever use a FF Lag in a construction programme

Just because the software allows you to do it there is no situation in the construction process that is represented by a FF Link.

Only ever use FS links.

If you a putting in a SS link with a lag you are really using a FS link except that you are guessing where the finish point is.

Best regards

Mike Testro