Resource hours

1 reply [Last post]
Gordon Bennett
User offline. Last seen 10 years 42 weeks ago. Offline
Joined: 4 Nov 2003
Posts: 4
Groups: None

I have just started on a project. When I review Budgeted resource hours on the activity they are 8 times higher that what the other planner sees. How do I resolve ?

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Sometimes this happes when you convert a p3 project to p6 

1. check your resource default units/time it would be 8

to fix this run a global change 

where budgeted units is greater than 8 then 

budget units equals budget units / 8