Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource hours

1 reply [Last post]
Gordon Bennett
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 4 Nov 2003
Posts: 4
Groups: None

I have just started on a project. When I review Budgeted resource hours on the activity they are 8 times higher that what the other planner sees. How do I resolve ?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Sometimes this happes when you convert a p3 project to p6 

1. check your resource default units/time it would be 8

to fix this run a global change 

where budgeted units is greater than 8 then 

budget units equals budget units / 8