Exporting Relationships to Excel

1 reply [Last post]
Robert McGhee
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 27 Mar 2008
Posts: 15
Groups: None

When exporting activity relationships to Excel, only get 10 characters in the predecessor & successor activity names, but when I export activities, get the entire name.   How do I expand the number of characters in the relationships export?

Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 days 8 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

one thing to do it to create a Vlookup in the TASKPRED tab that references the TASK tab in excel.