Need to configure database every time I log in P6 8.3.2

3 replies [Last post]
Alan Orangi
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 7 Jan 2010
Posts: 6
Groups: None

Dear All,

Recently every when I want to log in P6 it asks me to configure database! I didn't have this problem before. would you please advise?

Also it take a long time (around 3 minutes) for P6 to come up , also it didn't have this issue before.

Would you please advise on what could be the problem?

Thank you in anticipation.

Regards.

Alan

Replies

Dieter Wambach
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Alan

What does happen if you'll reestablish the link? I remember that in an earlier version there was some trouble with the file where the configuration information is kept. The number of configurations was restricted.

Good luck!

Dieter

Alan Orangi
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 7 Jan 2010
Posts: 6
Groups: None

Hi Dieter,

Thanks for the message. I thought it might be an installation problem myself so I unintall and re-install it, but still had the same problem. What interests me that P6 has been on my computer for a few months and these problems starts a couple of days ago.

 

Thanks you,

Alan

Dieter Wambach
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Alan

There is something wrong with the installation. Backup your database and install once more. There is file with all your db accesses/configurations. Let IT check why P6 cannot read this information during start-up.

Second possible reason: A conflict with an antivirus software.

In both cases your IT should be able to solve this issue.

Good luck!

Dieter