Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Percentage complete type on P6

2 replies [Last post]
Saqib Ali
User offline. Last seen 5 years 43 weeks ago. Offline
Joined: 26 Jun 2012
Posts: 6
Groups: None

Hello Planner's,

How are u?

I'm searching the definition & diference between percentage complete like Duration per%, Unit Per%, Phisycal Per%, Performance per% & Schedule percentage. what the effect of these percentage on schedule & where were we use it.

 

Many Thanks

Saqib Ali

Replies

Saqib Ali
User offline. Last seen 5 years 43 weeks ago. Offline
Joined: 26 Jun 2012
Posts: 6
Groups: None

Thank Manochehr Hosseini for this helping link but this link not opened my window when i opened it show me the Page not Found message.

 

my second question if we making Revenue Curve and we have the project BOQ. Then how will we achieved the planned amount for every month remaining the project duration. 

Manochehr Hosseini
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 1 Feb 2003
Posts: 35