Primavera setting to keep deleted Activity IDs from being automatically generated

1 reply [Last post]
Chris Feagan
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 15 Nov 2013
Posts: 5
Groups: None
Is there a Primavera setting that will keep deleted Activity IDs from being automatically generated in Primavera 6 Rev 8.2? We normally utilize the "auto-numbering" capabilities within Primavera, but have noticed that deleted Activity IDs are being re-created, thus causing some confusion in our network. Because there are numerous personnel that report on our data, the fact that Activity IDs are regenerated after a task in deleted causes the major confusion.

Replies

France Tintinger
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 7 Feb 2007
Posts: 11
Groups: None

Hi Chris

First close the project you are working on.

Go to the closed project in the Projects section and change your auto-numbering Defaults for new activities in the Defaults tab to have either a new Activity ID Prefix and/or a new Activity ID Suffix. For ex. your previous activities were in the format A1000, A1010 and so on. Change the Activity ID Prefix to AN1 before adding newly created activities. Now your new activities will start with AN1 (the N1 in this case standing for New1. If activities are added later, change the Activity ID Prefix to AN2 and so on).