Is it possible to set up automatically generated reports

1 reply [Last post]
Shaun Chew
User offline. Last seen 6 years 5 days ago. Offline
Joined: 4 Dec 2015
Posts: 5
Groups: None

Hello,

I have created a few reports that i need to generate weekly at certain times ( after the weeks schedule has finalised and also at the end of a week when all schedule updates have been entered ). These also need to be generated at specific times of the day, is this possibble to set up in P6 V.7

Thank you

Replies

Zoltan Palffy
User offline. Last seen 6 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

yes this can be done through the Tools Job Services utility. Using the Job Services you can tell it to Apply Actuals, Batch Reports, Export, Schedule, or Summarize.