Cant able to chnage outline(indent or outdent) of the Task

3 replies [Last post]
Nathan Siva
User offline. Last seen 1 week 1 day ago. Offline
Joined: 28 Apr 2014
Posts: 22
Groups: None

Hi Experts,

I can't able to change outline level (indent or outdent) my project task, I already checked, there is no grouping, Sorting and filter applied.

The project which i'm working have external links

Kindly guide.

Replies

Alexandre Faulx-B...
User offline. Last seen 1 day 6 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1285

Nathan,

I hope this will help you:

on image natan1, select Task B and click the tool inside the red square

you should obtain the result in image nathan2.png

alexandre

7326
nathan_1.png

 

 

 

 

 

7327
nathan_2.png

Nathan Siva
User offline. Last seen 1 week 1 day ago. Offline
Joined: 28 Apr 2014
Posts: 22
Groups: None

Hi Alexandre,

Thanks for your suggestion, But I'm still facing the same issue, even after I used indent tool, it's not showing any changes in outline level.

Alexandre Faulx-B...
User offline. Last seen 1 day 6 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1285

Hi Nathan

I am not sure to understand where your problem stands;

let's do the following

select the second task in the spreadsheet, then in the Task tab of the ribbon click on the Indent tool (the small arrow looking to the right)

as far as I know there is no functionnality ins MS Project to disable indenting/oudenting tasks in a project

All the best,

Alexandre