Working Hours Issue

1 reply [Last post]
Irfan Chaudhry
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 15 Mar 2014
Posts: 3

Dear All,

 

I want to creat a calendar with working hours 10:00 PM to 05:AM,but as i try to creat a calendar and change the time its doesn't work...when i try to put start of time as 10 PM it automatically pick the finish time with  one hour increment as 11 PM.or if put finish time 03:00 AM it gives the start time 02:00 AM.....Can you please help me on this..

Replies

Irfan Chaudhry
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 15 Mar 2014
Posts: 3

Thank you Jerome..appreciat your help.

 

Jerome Odeh
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 19 Jan 2004
Posts: 102

Irfan,

You need 2 rows of time periods.

  1. In Row 1, enter 20:00 in the From column and edit the 21:00 in the To column & make it 00:00
  2. In Row 2, enter 00:00 in the From column and edit the 01:00 in the To column & make it 05:00
=jerome