Headings / Non-Summary tasks without dates / durations etc

3 replies [Last post]
Christine P
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None

Hi

Is it posible in MSP2013 to make a plain old heading?

I just want a title (not header) above sections of some of my tasks, I don't want a date or duration or anything assigned to them, just a plain old title at certain sections. 

The only thing I've found of help on the internet is to summarise them in a hammock bar.  But that will make my Gantt chart untiday as I dont want hammocks everywhere. 

I know it was do-able in Asta Powerproject, is it possible in MSP please? 

Replies

Christine P
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None

Ismet

You are a gem, thank you

Ismet Kocaman
User offline. Last seen 8 years 24 weeks ago. Offline
Joined: 5 Mar 2010
Posts: 26

You can enter a placeholder task (a manually scheduled task with no duration and start/finish dates, instead, just blank). Set task mode to manual and then format the task name as a header. 

Christine P
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None

I'm guessing it's not possible