Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Summary Task Duration Display

3 replies [Last post]
Tony McClennon
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 19 Nov 2002
Posts: 97
Groups: None
Can anyone advise whether or not it is possible to show the duration of the summary tasks in anything other than days?

I have been trying to set the summary bar to show the duration in weeks or months, but have failed to achieve this so far.

Over to the MSP Gurus!!!

Cheers,

Tony

Replies

Tony McClennon
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 19 Nov 2002
Posts: 97
Groups: None
Sukumaran - many thanks, just the thing.I must have been having one of those "forgetful" moments!!!

Regards,

Tony
Sukumaran Subaram...
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Go to Tools > Options > Schedule and in the following field "DURATIONS IS ENTERED IN" change to either Weeks or Months.

Regards.
Tony McClennon
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 19 Nov 2002
Posts: 97
Groups: None
Sorry - should have mentioned that I am working with MSP2000.

Tony