Baselines on MSP

2 replies [Last post]
John Kelly
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 18 Jul 2011
Posts: 25
Groups: None

Hi Guys,

 

Question and apologies if this is an easy one.  i have 7 updated MSP programmes for a project, December through to June.  The Critical Path is through the same section of works for each month.  I want to set the previous month as the basline for each month and also maybe set December as the Baseline for June to show As Planned Vs As built.

How do i do this, ie set a different MSP programe as a baseline. Is it a problem that as the project progress more detail was added into the Programme, more activities, therefore act ID 43 will not match with Activity ID 43 for a later programme.

 

Thanks in advance.

Replies

Ismet Kocaman
User offline. Last seen 9 years 41 weeks ago. Offline
Joined: 5 Mar 2010
Posts: 26

You can test it as follows:

- Just save 2 baselines: Baseline 1 and Baseline 2.

- Add any Project field for both Baseline 1 and Baseline 2 (e.g. Baseline 1 Duration and Baseline 2 Duration) to the table (e.g. Entry table of the Gantt Chart View).

- Practice and see how the fields change as you modify the task list by deleting, inserting, moving task lines.

Regards,

Ismet

John Kelly
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 18 Jul 2011
Posts: 25
Groups: None

Apologies saved two of these by accident!!! (won't happen again Mike, just realised that saving actually posts it!!!)