Hi Guys,
Question and apologies if this is an easy one. i have 7 updated MSP programmes for a project, December through to June. The Critical Path is through the same section of works for each month. I want to set the previous month as the basline for each month and also maybe set December as the Baseline for June to show As Planned Vs As built.
How do i do this, ie set a different MSP programe as a baseline. Is it a problem that as the project progress more detail was added into the Programme, more activities, therefore act ID 43 will not match with Activity ID 43 for a later programme.
Thanks in advance.