sheduling consective tasks with a must start directly after previous task

HI, does anyone have any fixes which would allow me to create a link or constraint which would hold two tasks together so that wherever they were scheduled they would stay together, ie if task one is scheduled for monday and lasts one day task two must start on tuesday or vice versa if task two was scheduled for a tuesday task one must be scheduled for monday. The logical sequence is obviously there but when you resource level there is nothing to group them together. I know it sounds simple but it aint

Alex

 

A
alex mclellan 👤 Member for 14 years 8 months

unfortunately i need to relevel my resources regularly. thanks anyway

alex

M
Mike Testro 👤 Member for 20 years 5 months

Hi Alex

Use a single FS link between Task A and B.

Then set task A ALAP.

If you allow the software to level your resources then it will over ride any logic that you have previously set up.

That is why it should never be used.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts