Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

problem with percent complete

1 reply [Last post]
kp rao
User offline. Last seen 11 years 6 weeks ago. Offline
Joined: 29 Jul 2011
Posts: 18

Dear all,

I am using Ms project 2007.Physical percent complete progress  bar not showing correctly.And also I want to show progress line based on physical percent complete.is it possible.When I try this progress line showing based on % complete not Physical percent complete.

And also I have problem while using duration per compelte.suppose the site team reports 90% and i update this the finish date changes to some other date.But I want to control finish date and keep 90%.is it possible.

Regards,

kp

Replies

Darren Kosa
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 256
Groups: None

Hi kp,

Firstly I would suggest you make a copy of the Gantt Chart view for this, (View > More Views > Gantt Chart > Copy) and then use this view to change your Bar Styles (Format > Bar Styles).

In the Bar Styles Dialog Box find the Progress row and change ‘CompleteThrough’ in the To column to ‘Physical % Complete’.

When now you manually enter values in the Physical % Complete column in your Table it should be shown as a progress line on the Gantt Chart. Please be aware that Physical % Complete will only show at Task level and does not roll up to Summary Task level.

Your second question is a little trickier to answer as I don’t know how you update MS Project. I generally update schedules using Actual and Remaining Duration/Work, and don’t enter values against % Complete.

Does the Task ‘Split’ when you enter your % Complete? If it does then you may want to uncheck the ‘Split in progress tasks’ option (Tools > Options > Schedule).

It may also be related to a Calculation Option you have selected. Try unchecking the ‘Move end of / start of completed / remaining parts’ option (Tools > Options > Calculation).

Hopefully this will solve your problem, if it does remember to click the ‘Set as Default’ button on each of those tabs before you close down MS Project, or the problem might reappear when you open another file.

Regards,

Darren Kosa