Link remaining duration and schedule percent complete problem

1 reply [Last post]
Yaser A. Al-Bustanji
User offline. Last seen 1 year 11 weeks ago. Offline
Joined: 12 May 2010
Posts: 27
Groups: None

Dear Freinds

 

I have a schedule an auto cost rule linke remaining duration and schedule percent complete is unchecked and the schedule culcuates all value based on this situation when i change this (check the box) the remaining duration and pecent complete remain unliked  unless i change one of them manually.

 

How can i recuculate remaing durations based on the percent complete for all activities in the schedule

 

please advise

 

Regards

Replies

Paul Harris
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

Try running a global change after backing up you project.

The option only works when you change data not when you turn oin and off the option.

 

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au - a Primavera scheduling software resources site