Calculating Hours-Man with Project

2 replies [Last post]
Jhorbam Baena Orozco
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Hi...with Primavera Project Planner i can get the report of the Hours-man neccesaries to complete the project...but i not found a similar option in Microsoft Project...an option that i can use to get that information calculated by the Microsoft Project...

Can someone tell how i can get that report?...or that option are not able in Microsoft Project?

Thanks

Replies

Rodel Marasigan
User offline. Last seen 2 days 10 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Jhorbam,
Try View-> Task Usage or View-> Resource Usage. You can insert the column that you want to show like Baseline Work, Work, Remaining Work, Actual Work...etc. You can also apply groupings.
Trevor Rabey
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Remaining Work?
See the Work Table.