Changing Date ..Man Hours Change

2 replies [Last post]
zulfi Ali
User offline. Last seen 13 years 1 week ago. Offline
Joined: 16 Nov 2004
Posts: 17
Hi Friends, I

I have a problem and need your help to fix it ut. I work on P3 but, had to work on MSP.
Whenever I change activity duration and date , activity resource manhours also change, could you please help to fix it up.

Thanks

Replies

zulfi Ali
User offline. Last seen 13 years 1 week ago. Offline
Joined: 16 Nov 2004
Posts: 17
Thank you very much Alexandre. Only one activity still showing the same attribute. Let’s see
Once more thanks a lot for your kind information.
Alexandre Faulx-B...
User offline. Last seen 2 days 20 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1253
Ali,
Double-clic the task to open "Task Information", display "Advanced", change "Task Type" to "Fixed Work" to have the assignement rate changed instead of the amount of work.
Select together all the tasks you want and click the Task Information icon, then continue as above
Open Tools, Options, Schedule and change Task Type to Fixed Work to setup the tasks before you create it.
All the best