MSP 2007 SP1 – EV Bug report

No replies
Nader K. Rad
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 2 Jan 2007
Posts: 46
Groups: None
I have one task, with 1 assigned work resource (more than 100% unit). My only cost is resource per use cost.
Now, I have my baseline saved, and my task %complete is more than 0%. here is my resource sheet:
Resource information:
BCWP: 8350$
BCWS: 100$
ACWP: 100$
Cost: 100$
Task information:
BCWP: 100$
BCWS: 100$
ACWP: 100$
Cost: 100$
As you know, this resource BCWP should be 100$, but IT IS NOT!!!
This problem would not occure, if assignment unit is 100% or resource per use cost is 0$ (other costs would not make problems).

:(