Custom Resource Curves

2 replies [Last post]
Hemanth Kumar
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
Can we make custom resource curves in MSP

none of the default Curves(Bell,Turtle Etc) match My Resource

Replies

Hemanth Kumar
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
thank you mr james

but i want to create a resorce profile template ( As I Do In P3)
and use it for my activity

i will be entering for an activity : duration,resource profile and budjeted qty, i dont know on what day how much resource, but want to know that.....


thanks
James Griffiths
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Hi Hemanth,

Yes you can input a custom resource curve against every individual resource on every individual task. All you need do is go into the Task Usage or Resource Usage View. Make sure that the right-hand side of the screen is showing WORK, then input the daily hours that you expect the resource to work. Of course, you must have allocated a resource to the task in the first place

I will say, though, that the whole exercise is nearly a complete waste of time. As soon as you input ACTUALS, the system will automatically re-schedule the profile according to the Task Type(Fixed Work, Fixed Duration or Fixed Units) and the amount of work previously done.

James.