Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Master and Sub-Projects??

3 replies [Last post]
Allison Robb
User offline. Last seen 19 years 27 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 9
Groups: None
Is there a clever way of setting up a master project within MS Project 2002. We are trying to reduce the amount of manual updates from plans submitted to a central project office.

Replies

Robyn Brown
User offline. Last seen 14 years 30 weeks ago. Offline
Joined: 18 Dec 2004
Posts: 10
Groups: None
Hi All,

It is possible to provide a quick and easy way to consolidate all the projects. Once the filters etc. are defined it can be done automaticccccaly.


Regards
Robyn
Tony McClennon
User offline. Last seen 1 year 28 weeks ago. Offline
Joined: 19 Nov 2002
Posts: 97
Groups: None
Would suggest that you set up a template to be used by all of the sub-projects, which have common calendars, customised fields, headers/footers, bar styles etc.

You may also wish to consider using one of the text fields as a predefined task numbering system e.g.:

XX-YYY-ZZZZZ

where XX relates to the sub-project, YYY is the high-level WBS within the sub-projectm and ZZZZZ are the unique task IDs.

Hope this is of use.
Paul Harris
User offline. Last seen 2 weeks 5 days ago. Offline
Joined: 11 Apr 2001
Posts: 618
You may use the Insert, Project Command and insert as many projects as you like.

I suggest you use this option with caution, there are many issues with this option.

I prefer just cutting and pasting the tasks from one project into another, but then the calendars have to match before doing this. You may consider setting an Interim Baseline to confirm the tasks that are passed in are calculating correctly after insertion.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au