Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual Work

1 reply [Last post]
Forum Guest
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
Is there any way of LOCKING the actual work field. Whenever I explore changes in resources, time, duration - my (past)actual work figures alter.

Replies

David Barry
User offline. Last seen 19 years 51 weeks ago. Offline
Joined: 29 Feb 2004
Posts: 3
Groups: None
Make sure "effort driven scheduling" is not operational.