Hi Everyone,
I am working for a contractor who is 2 years over a 2 year duration project. Only one programme has been approved by the Owner, however none other of the 6 further subsequent revisions which reflect the alterations site have been approved.
This may be going to arbitration and a TIA will be used; works have been completed.
The final revision contains much more details and additional activities than the baseline, therefore the as-built won't match.
During the TIA does every activity of the as-built have to match exclusively or can I apply an as-built at a higher level on the WBS.
It would be great to re-build an as-built using the original baseline, but there are areas not captured, therefore the problem.
Say , the baseline of a rail station box contained 3 levels (Platform-Concourse-Entrance), 6th revision of updated schedule and thus as-built, contains 5 levels.
Thank you.
Replies