Difference btwn Time Impact Analysis & Delay Analysis
Hi Analysts
Would any one tell me the difference between Time Impact Analysis and Delay Analysis
Cheers
Tanveer
Hi Andrew,
I don't think we need to split hairs as to whether IAP & TIA are 'different' or 'very different'.
I think we can both agree the two techniques differ as you've outlined and are not one and the same as implied in your earlier post.
Best Regards,
Chris Hall
Chris,
Impact-as-planned and Time impact are not very different.
Delay Analysis in Construction Contracts
By P. John Keane, Anthony F. Caletka
"The main difference between the TIA & IAP methods is the use of 'multiple base' programmes in the TIA, as opposed to a 'single base' (i.e. the baseline) in the IAP.
Dear Mr. Tastro
I am sorry for revealing the dead topic; I posted the thread coz I really didn’t find my answer. I was confused as I saw a clip on http://www.youtube.com/watch?v=RRhbzfY2aRw which says that the Time Impact Analysis is a forecast impact of an expected event. I think I got my answer that it’s the difference btwn the US and the UK terminologies, if I understood you right.
Thanx - Cheers
Hi Tanveer
The definition of Delay Analysis terms depends on if you are British or American.
Time Impact Analysis and Impacted as Planned are interchangeable between the two jurisdictions.
I tried a while back to get common terms established but our US friends were entrenched.
Now - whenever I use a term in a report I classify it as "SCL Protocol Defined" in a footnote so as to avoid any confusion.
Best regards
Mike Testro
Hi Hall
You are right - sorry.
Best regards
Mike Testro
Hi Mike,
I may be mistaken but i thought the thread was started today?
If i've stirred up a topic from PP's past, appologies. Still feeling my way around PP.
Chris
Hi Hall
Perhaps you didn't realise but you have just responded to a 7 year old thread.
It is not a good idea to liven up long dead topics.
Best regards
Mike Testro
Andrew,
Don't get Time Impact Analysis (TIA) confused with Impact As-Planned (IAP).
Very difference techinques.
Chris
Time impact analysis or 'impacted as-planned' analysis is one of several delay analysis techniques. The impacted as planned method consists of listing all the excusable delays (or delays where time extension is owed to the contractor) and adding this extended duration to the relevant activities to determine the revised completion date. The difference between the revised completion date and the as-planned completion date determines the number of days owed to the contractor.
Tan,
Time Impact Analysis is a Delay Analysis technique. Some other techinques include; impacted as planned (IAP), Collapsed As Build & comparative i.e. as planned vs. as built, plus more.
There are good books around on this, I would recommend Delay Analysis in Construction Contracts by P.J.Keane & A.F.Caletka (Wiley-Blackwell Publishers) which is worth a read. And, if you know where to look it is avaliable free on the web.
Chris
Replies