Impact-as-planned and Time impact are not very different.
Delay Analysis in Construction Contracts
By P. John Keane, Anthony F. Caletka
"The main difference between the TIA & IAP methods is the use of 'multiple base' programmes in the TIA, as opposed to a 'single base' (i.e. the baseline) in the IAP.
I am sorry for revealing the dead topic; I posted the thread coz I really didn’t find my answer. I was confused as I saw a clip on http://www.youtube.com/watch?v=RRhbzfY2aRw which says that the Time Impact Analysis is a forecast impact of an expected event. I think I got my answer that it’s the difference btwn the US and the UK terminologies, if I understood you right.
Time impact analysis or 'impacted as-planned' analysis is one of several delay analysis techniques. The impacted as planned method consists of listing all the excusable delays (or delays where time extension is owed to the contractor) and adding this extended duration to the relevant activities to determine the revised completion date. The difference between the revised completion date and the as-planned completion date determines the number of days owed to the contractor.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Chris,
Impact-as-planned and Time impact are not very different.
Delay Analysis in Construction Contracts
By P. John Keane, Anthony F. Caletka
"The main difference between the TIA & IAP methods is the use of 'multiple base' programmes in the TIA, as opposed to a 'single base' (i.e. the baseline) in the IAP.
Dear Mr. Tastro
I am sorry for revealing the dead topic; I posted the thread coz I really didn’t find my answer. I was confused as I saw a clip on http://www.youtube.com/watch?v=RRhbzfY2aRw which says that the Time Impact Analysis is a forecast impact of an expected event. I think I got my answer that it’s the difference btwn the US and the UK terminologies, if I understood you right.
Thanx - Cheers
Hi Tanveer
The definition of Delay Analysis terms depends on if you are British or American.
Time Impact Analysis and Impacted as Planned are interchangeable between the two jurisdictions.
I tried a while back to get common terms established but our US friends were entrenched.
Now - whenever I use a term in a report I classify it as "SCL Protocol Defined" in a footnote so as to avoid any confusion.
Best regards
Mike Testro
Hi Hall
You are right - sorry.
Best regards
Mike Testro
Hi Hall
Perhaps you didn't realise but you have just responded to a 7 year old thread.
It is not a good idea to liven up long dead topics.
Best regards
Mike Testro
Time impact analysis or 'impacted as-planned' analysis is one of several delay analysis techniques. The impacted as planned method consists of listing all the excusable delays (or delays where time extension is owed to the contractor) and adding this extended duration to the relevant activities to determine the revised completion date. The difference between the revised completion date and the as-planned completion date determines the number of days owed to the contractor.