Notification during Suspension

4 replies [Last post]
khawaja uddin
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 59
Groups: None
Hi all
One of the project is under suspension .....during this ongoing suspension period ,we need to notify to Engineer for the delay events as per the FIDIC 20/1......ARE WE SUPPOSE TO NOTIFY THE DELAYS AFTER THE RECOMMENCEMENT OF THE WORK......OR THE 28 DAYS ARE STILL COUNT EVEN IN THE SUSPENSION PERIOD...

Hope I could clarify my view point and look forward for the response
Thanks/Regards

Replies

Mohamed AL Sherbiny
User offline. Last seen 14 years 47 weeks ago. Offline
Joined: 4 Feb 2009
Posts: 11
Groups: None
Dear Khawaja,

Surely,
you have to notify the engineer about any impact of suspension occurred, as long as that
* would impact your payments (according cost incurred from suspension)
or/and
* affect your resposibility to :
* protect works (in progress or completed)
* securing the suspended works against deterioration, loss, or damage.
* affect the level of quality to works and/or materials in site (Works material, and not construction material), that is would not comply with specificatins any more.

I hope that works with you,

Your feed back is welcomed

Mohamed
Mike Testro
User offline. Last seen 6 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Khawaja

Make sure that you set the suspension period into your calendat as a series of Non Work days.

This will establish the delay effect on all activities.

Best regards

Mike Testro
khawaja uddin
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 59
Groups: None
Dear Sherbiny
Thanks for your prompt reply.
If any other works is delayed due to the suspension(and suspension is still going on).Do we need to send the notices for those delays as well ,DURING SUSPENSION, complying to the FIDIC????

Hope to recieve your and others comment on the situation
Thanks
Khawaja
Mohamed AL Sherbiny
User offline. Last seen 14 years 47 weeks ago. Offline
Joined: 4 Feb 2009
Posts: 11
Groups: None
* You have to notify the Engineer about you intentions if you know and determine the suspension starting day.

Or,
* Notify him when you start the suspension.

* Don’t forget to state your reference for that action (clause # ....), and list your reasons.

* Do not forget to reassure that the Employer received his copy

* notify the engineer and copy to Employer about the status of project activities, material on site, and personnel in charge (staff and labors), and what is expected dialy attendees in site.

* if still no action from the employer, notify the cost incurred monthly, and impacts facing and expecting, and the expected monthly claim ammount.

* after negotiations and ending the suspension period , send the results of negotiations, and new status of the project.


I hope that helping

Mohamed