DESIGN AND BUILD CONTRACT

3 replies [Last post]
mark fernando
User offline. Last seen 16 years 13 weeks ago. Offline
Joined: 23 Jan 2009
Posts: 5
Groups: None
HOW CAN A CONTRACTOR CLAIM FOR EOT IN DESIGN AND BUILD CONTRACT.

REGARDS,


ABDALLAH RIAD

Replies

Mike Testro
User offline. Last seen 26 weeks 7 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Mark

I forgot to mention - please do not use captial letters in your contributions - it sounds as if you are shouting.

Best regards

Mike Testro
Samer Zawaydeh
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear mark,

I agree with Mike, you need to check each clause in your Contract. From the time you were handed over the site and all the information provided by the Client.

Plenty or issues:
Site, permits, safety and security, cash flow, Free Issue Material, instructions of Engineer, Extras, scope change, unforeseen physical conditions.

Best Regards,

Samer
Mike Testro
User offline. Last seen 26 weeks 7 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Mark

Just because a contract is design and build does not preclude the usual EOT methods.

The source of the delay events may be limited to exclude late design information.

Late client changes or unforeseen circumstances may still be relevant.

Check the Contract to see what delay events are relevant to an EOT and focus on those.

Best regards

Mike Testro