Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Delay in Subcontractors Nomination

9 replies [Last post]
Khalil Masoud
User offline. Last seen 16 years 44 weeks ago. Offline
Joined: 14 Oct 2007
Posts: 19
Groups: None
Gentlemen;

I am working with the Client Representative team and would like to discuss our part of delay regarding the nominated subcontractors.

The project is already late by the Contractor by 4 months. However, some nominations for subcontractors are also late due to the client’s slow system. But the late nominations are not delaying the project at this moment. However, the Contractor keeps claiming for his entitlement for time extension thru impact schedule.

My question is: Can the Contractor be considered entitled for extension of time although he is already late in his part of construction??? in other words, even if we nominated on time, this will not make him start the works related to our nomination early???

your comments are highly appreciated

Replies

Waleed Mahfouz
User offline. Last seen 9 years 7 weeks ago. Offline
Joined: 8 Sep 2007
Posts: 28
Groups: None
Dear khalil masoud,
This depends upon the method you decided to calculate the delays. If you consider the updated schedule you will be able to separate between the delay caused by the general contractor and you as owner representative.
However the time impact based on the programme clause 14.1 you will not be able to separate between the causes of delay. in addition the total float will be considered for the benefit of the project itself, so delay will be calculated after dissipation of total float. Also the delay analysis will show the responsibility of each party.
Khalil Masoud
User offline. Last seen 16 years 44 weeks ago. Offline
Joined: 14 Oct 2007
Posts: 19
Groups: None
Hi Graham;

This subcontractor’s schedule shows criticality in terms of Total Float, but the relationships in the programme show dependency on something that is not yet reached physically (Floor#10) and currently the contractor is at floor#3!!! even though, the update shows critical activities for the subcontractor, but i think this is misleading, because even if we (as client representative) nominated on time, the subcontractor cannot commence his works according to the logic of the original baseline because the actual progress is already late.!!!!the General Contractor has to reach level 10 first according to the logic(relationships) inherent in the approved baseline, but currently he is at level3!!! any tips??
thank you
Graham Glassey
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 3 Jan 2002
Posts: 6
Groups: None
Khalil

Is the work to be carried out by the nominated Subcontractor critical to the completion date of the Project? If it is not then no EOT is due but there may be compensation due in the form of disruption.

Just because an employer delay occurs does not mean that the Contractor is entitled to an EOT.

Graham
Waleed Mahfouz
User offline. Last seen 9 years 7 weeks ago. Offline
Joined: 8 Sep 2007
Posts: 28
Groups: None
Delay in nominating subcontractor give the contractor the right to claim for EOT. You have to prepare the time impact on the approved baseline schedule, that matches fidic as the total float is owned to the project.
Andrew Flowerdew
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Ashraf,

Late nomination would normally give rise to an entitlement for an EoT but comes down to the wording of your contract. On what basis does your contract say EoT’s are granted - eg, likely delay or actual delay. Any provisions dealing with concurrent delays, (probably not)? Any delay has to be related to the progress of the works, not the original baseline, so the Employer might be late, but if the contractor is also, the employer might not be causing any delay.

Too little information to form any conclusions, could be anywhere between zero and 5 months EoT due.
ashraf alawady
User offline. Last seen 10 years 42 weeks ago. Offline
Joined: 27 Aug 2006
Posts: 320
Groups: None
before issuing the nomination of the subcontractor as delay event which well known earlier, you have to have up gate progress report in which you observed 4 months delays from the contractor side.
study the impact of the delay ,in issuing the approval and nominating the subcontractor,on the approved baseline program taking into consideration the realiestic program of the nominated subcontractor to complete his job.
Roger Gibson
User offline. Last seen 7 years 43 weeks ago. Offline
Joined: 1 Jun 2001
Posts: 71
Khalil,

This should be done before the nomination is issued to the contractor so that no extension of time is due. I would also, as a separate issue, request that the contractor produces a revised programme showing how he is going to recover his current 4 month critial delay.

Roger Gibson

Khalil Masoud
User offline. Last seen 16 years 44 weeks ago. Offline
Joined: 14 Oct 2007
Posts: 19
Groups: None
Thanx Roger;

I am quoting your sentence: "The contractor may then argue that he is entitled to a 5 month eot, as he intends to recover his own 4 month delay ...."

What if We "as client representative" intend to recover our own delay by asking the prospective nominated subcontractors to submit a new recovery schedule meeting the originally planned baseline regarding the client’s part??

thank you
Roger Gibson
User offline. Last seen 7 years 43 weeks ago. Offline
Joined: 1 Jun 2001
Posts: 71
Khalil,

If the project is currently 4 months late, i.e. the current progress update of the project shows that completion of the project is forecast to be 4 months later than the contract date, then if the contractor can demonstrate, through a ’time impact’ analysis that a client’s nomination is likely to delay the contract completion by say 5 months then he is entitled to an extension of time of 1 month. The contractor may then argue that he is entitled to a 5 month eot, as he intends to recover his own 4 month delay (by additional overtime, increased resources, etc).

All this is subject to the conditions of the Contract between the client and contractor.

Roger Gibson