Hi Planners,
Gotta problem. Will appreciate any comments on the following.
“Clause 58.2 – Use of Provisional Sums
In respect of every Provisional Sum the Engineer shall have authority to issue instructions for the execution of work or for the supply of goods, materials, Plant or services by:
a) the Contractor, in which case the Contractor shall be entitled to an amount equal to the value thereof determined in accordance with Clause 52;
b) a Nominated Subcontractor, as hereinafter defined, in which case the sum to be paid to the Contractor therefore shall be determined and paid in accordance with Sub-Clause 59.4 (Payments to Nominated Subcontractors).
Clause 59.3 – Design Requirements to be Expressly Stated
If in connection with any Provisional Sum the services to be provided include any matter of design or specification of any part of the Permanent Works or of any Plant to be incorporated therein, such requirement shall be expressly stated in the Contract and shall be included in any nominated Subcontract. The nominated Subcontract shall specify that the nominated Subcontractor providing such services will save harmless and indemnify the Contractor from and against the same and from all claims, proceedings, damages, costs, charges and expenses whatsoever arising out of or in connection with any failure to perform such obligations or to fulfill such liabilities.”
The said nominated subcontractor is a Post Tensioning subcontractor as appointed by the Client.
The Engineer and the Client revised design of a structural slab and held a meeting with the nominated Subcontractor regarding the redesign of the slab for post tensioning works without the knowledge of the Main Contractor.
The Main Contractor objected to the meeting of the Nominated Subcontractor, Client and the Engineer without the knowledge of the Main Contractor. The Engineer rejected the objection of the Main Contractor stating clause 58.2 (above).
Now, my question is –
a) Has the Main Contractor any right to make any claim or objection to such meetings between the Nominated Subcontractor, Client and the Engineer without the knowledge of the Main Contractor?
b) Can the Main Contractor penalize the Nominated Subcontractor for taking instructions directly from the Client / Engineer?
c) Can clause 59.3 (as above) be utilized in the best interest of the Main Contractor, especially in such cases?
Looking forward for ur valuable comments.
Rgds,
Replies