Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

on termination

2 replies [Last post]
Francis Moyalan, ...
User offline. Last seen 4 years 49 weeks ago. Offline
Joined: 12 Feb 2005
Posts: 105
Groups: None
hello there,
the case goes something like this...

my company got a road project in the year 2001,

completion date was in 2003,

project got delayed due to concurrent delays...

i.e both from contractor’s as well as from client’s side...

in this year the employer took the decision to invoke the performance guarantee and encashed it...

arbitration was going on before encashment...

in this situation can the company get any claim if it’s going with the arbitration?

I will be thankful for any sensible suggestion on this issue,

bye

Replies

Shahzad Munawar
User offline. Last seen 8 years 51 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Hi francis

1) Firstly this all depends upon that what your Contract Provisions says upon termination

2) Secondly you can claim your damages/losses arisen from such termination if your Contract possess Clause of Termination for convenience of Client which stipulates that the Contractor can submit a Final Termination Settlement proposal to the Client.

3) Thirdly in case of such termination, arbitration is only one way where you can cover your lossess if prove.
MK TSE
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Is any "conflict" between arbitration and performance guarantee matter?
Contract conditions be reviewed on this issue.