Float and dates don't nake sense

3 replies [Last post]
Catherine Groves
User offline. Last seen 3 years 11 weeks ago. Offline
Joined: 3 Apr 2014
Posts: 5
Groups: None

 I have a schedule with a must finish by date of 6/24/21. The early finish for the project is 6/29/21, so about 5 days behind schedule. But it is showing -170 days of total float. I am not sure where this is computing from. The imposed finish is 6/24/2021 in properties. I have never had this happen before. Is there something I should at?

All my other projects are showing correct float. It is only this one.

Thanks

Replies

Stephen Devaux
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 23 Mar 2005
Posts: 667

Hi, Catherine. The good news is that if you need to compress your schedule by 5D, in Asta Powerproject you are using one of the very few software packages (along, notably, with Spider Project) that does the CPM computation of critical path drag that facilitates that process.

Fraternally in project management,

Steve the Bajan

Catherine Groves
User offline. Last seen 3 years 11 weeks ago. Offline
Joined: 3 Apr 2014
Posts: 5
Groups: None

Thanks Ben. Will do. 

Ben Taunt
User offline. Last seen 21 weeks 3 hours ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Catherine,

Can you email your .pp file to support@elecosoft.com and mention the problem, and then we can see what is causing this.

Thanks,

Ben @ Powerproject