I have a schedule with a must finish by date of 6/24/21. The early finish for the project is 6/29/21, so about 5 days behind schedule. But it is showing -170 days of total float. I am not sure where this is computing from. The imposed finish is 6/24/2021 in properties. I have never had this happen before. Is there something I should at?
All my other projects are showing correct float. It is only this one.
Thanks