Near Critical Filter

1 reply [Last post]
Steve Church
User offline. Last seen 2 weeks 7 hours ago. Offline
Joined: 8 Feb 2004
Posts: 12
Groups: None

In Asta, how do we filter for “Near Critical” Tasks?

Replies

Alexandre Faulx-B...
User offline. Last seen 1 hour 8 min ago. Offline
Joined: 20 Jan 2003
Posts: 1331

Hi Steve,

In the View tab, open Filter and click New

Edit the Criteria #1 row, 

Select Specific activity types: tasks, milestones, then Next

Select Float (Slack?) and Criticity, then Next

Click Show activities with specified float (radio button # 4), Total float, Less than, and enter a value in the Duration field

As I am working with PowerProject in French, I hope you will understand my explanations

Alexandre