Asta Easyplan - End Date

1 reply [Last post]
Keiron O'Mahoney
User offline. Last seen 6 years 19 weeks ago. Offline
Joined: 4 Jun 2019
Posts: 2
Groups: None

Good morning,

I'm hoping someone can help me solve an issue which is probably glaringly obvious, but I just can't find out where. I'm far from experienced in Easyplan and nobody here in the office is either. 

I am trying to create a programme that currently extends into 2021, however strangely Asta is curtailing the project at the end of 2020 and I cannot for the life of me find out why. Is this a licencing issue, is there something simply I am doing wrong!

Thank you for any help

Replies

Ben Taunt
User offline. Last seen 1 year 45 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Keiron,

Certainly not a licensing issue - there is nothing we can do within the tool to restrict you planning out as far as you wish into the future!

Instead, it sounds to me as though your calendar or working pattern are set such that post 2020 is marked as "non-working time".  If you right click on your default calendar in the list on the left-hand side, please check the Finsh Date for your Working Pattern Assignment.  You might need to punt this out a few more years to open up the dates you need to see.

Let me know if that solves things.

Thanks,

Ben @ Powerproject