BAK Files

2 replies [Last post]
anu h
User offline. Last seen 6 years 31 weeks ago. Offline
Joined: 22 Oct 2016
Posts: 6
Groups: None

Everytime I save asta PP programme copy of BAK file created on the same folder. How do I stop this? Any help appreciated

Replies

anu h
User offline. Last seen 6 years 31 weeks ago. Offline
Joined: 22 Oct 2016
Posts: 6
Groups: None

Many thanks So this means if ASTA crashed inthe middle of writing a programme I wont  be able to open it from recent files if I turn this off?

Ben Taunt
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

File > Options > Edit Tab > Create BAK Files (backups)

However, if you turn this off you will disable the auto-backup funtionality of Powerproject...  BAK files are used to recover your work in the event of any issues.

Thanks,

Ben @ Elecosoft