Milestone

1 reply [Last post]
anu h
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 22 Oct 2016
Posts: 6
Groups: None

I downloaded free trial of latest ASTA version. ried to type a new programme, However, when I tried to create a milestone with '0' on duration column it wont allow me to do that. Normally on a milestone start date and finish time is same. But in my programme there is one day difference between start and finish time. It wont allow me to change it into same date on both columns. How do I create milestone? It seems some sort of setting but I cant figure it out ant help will be greately appreciated

Replies

Mike Testro
User offline. Last seen 47 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Anu - Welcome to planning planet.

There are a number of ways to create a milesstone.

1. Type "0d" days in the duration field.

2. Right click the task and select Options > Change Into > Milestone

3. Hold the end of the task and drag sharp left to turn it into a milestone.

I hope that helps.

Best regards

Mike Testro