ASTA
is there anybody tell me How multi-Currency work on ASTA?
Hi Raphael,
You need to go "Library Explorer". Under "Currency Unit" you can add unlimited currency. When you add new currency you also enter exchange rate.
After that it is all up to you.
1) you can right click on activity table such as excel and from Format Cells you can choose which currency you want to display. It will automatically convert new currency using by exchange rate.
2) I am not sure if you know in ASTA the same Column can be display on activity table more than once. For example you select cost and add twice to table. After that you right click on Colum and from table definition you can select one USD another EURO. The same activity and on the same cost you will display both currency.
If my answer is not cover your expectation please follow up Mike’s recommend. If help not cover your expectation ask to Mike who is GRU of ASTA and Project Management, I am sure he will know the answer J
Tekin
Hi Raphael
Welcome to planning planet.
Go to Help
Type currencies tick Display
Select the first on the list and you will find all the information you need.
Asta Help is much quicker than the PP forum.
Best regards
Mike Testro
PP Market Place:
Project Planning & Control Using Primavera P6: A user guide and training manual written for professionals who wish to learn how to plan and control projects in an established Primavera Enterprise environment with or without Resources & Roles. (Learning Materials & Books) Read more...
Replies