Does anyone know if ASTA has Iphone or Ipad Module?

Does anyone know if ASTA has Iphone or Ipad Module?

Thanks

B
Ben Taunt 👤 Member for 14 years 4 months

Hi Patii,

I'm not entirely sure that your post isn't an advert for application development services...  However, it does give me an excuse to update this thread on the development I mentioned earlier in the year!

Site Progress Mobile, a mobile application on Android & iOS to work in conjunction with Asta Powerproject, is coming in the New Year.  Hopefully Santa will be delivering a beta version to interested parties shortly after dropping off the rest of his Christmas presents.  A full launch will then follow including demonstrations at our National User Forum in London, 26th March 2014.

It is looking like an ideal tool for connecting the reality of the build with the office-based planners!

Ben

P
Patii Lockett 👤 Member for 12 years 5 months

Hi,

Developing ASTA for ipad by using ipad application development is not an easy thing, I really appreciate this effeort made. No doubt ASta App is great option for us who regulary use mobile devices.

B
Ben Taunt 👤 Member for 14 years 4 months

Hi Claudia,

Funnily enough, we have exactly such an app in development as we speak - perhaps you've seen a copy of our product roadmap?!?

The focus of our support for mobile devices will be around the easy reporting of activity progress from remote locations; in other words, the perfect tool to allow site managers to report actual progress against scheduled activity.  This will function regardless of network connectivity, so you don't have to rely on having Wi-fi/3G/4G on a building site!  It is also equally applicable to our customer base outside of construction who want to record progress information but without needing to use our existing timesheet system.

Do keep an eye on our website or sign up for our 'Powerlines' newsletters in order to receive updates on our release schedule for these new modules.

Best wishes,

Ben @ Asta

C
Claudia Owen 👤 Member for 12 years 10 months

I guess this is something that they should work on to. Having an ASTA app for most popular devices can be a best options for many users and members.



Regards,

Claudia Owen

M
Muqtada Khalid 👤 Member for 13 years

I am thinking I will use my Smart Board to project the game with big screen and sounds. This will certainly get my students engaged by bringing them up to the board, selecting the plays, and getting ipad application development help for answers from the audience. Looking forward to Friday already.

T
Tekin Guvercin 👤 Member for 19 years

Dear Derya,

ASTA has mobile application. Enterprise version also has free of Charge IPAD & IPhone reporting. This is simple and very effective module for Management. Please see presentation how it work from as following link.

http://www.youtube.com/watch?v=DucPxlhlCU0&feature=youtu.be&a

Report Template also modify and custumize for each project.

Please let me know if you need any more explanation,

you can get trial from www.astadev.com

 

Regards

 

Tekin

 

Forum Sponsor

Top Posters

MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts