Opening and closing a summary heading

1 reply [Last post]
Bo Johnsen
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 28 Feb 2006
Posts: 119
Hi all,

Is there an easier way of opening and closing a single summary heading than double clicking the summary bar on the Gantt chart? The "Show to x Levels" is also available but that applies to all summary headings and not a single one (or a few).

It would be logic that the "+" and "-" in the column just left of the "Line"-column opened and closed a summary like most other planning systems, but it don’t - or maybe I just have some wrong settings?

Any tricks / short cuts for this available out there?


Best regards,

Bo

Replies

Mike Testro
User offline. Last seen 29 weeks 8 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Bo

The double click is the quickest way to open/close a summary bar.

The + - column is when you are using "task per Line" mode with more that 1 activity on the same line.

This is very useful if you are doing repetetive tasks in different locations - Housing estates or High rise fit outs.

There are problems with Task per Line mode including

1. Cannot copy paste to the columns
2. Loss of criticality

Best regards

Mike Testro