GRD Minproc Planning Engineer
START Date:
March, 2008
END Date:
January, 2009 Auditing the contractors schedule according to construction overall schedule.
Compiling sub-contractors data and prepare Daily, Weekly and Monthly reports.
Taking the physical progress and compare with the sub-contractors reports and Updating progress in P6 (Level IV).
Preparing weekly key performance index report (KPI).
Preparing and auditing Quantity Man-hours Report (QMR).
Preparing and Maintaining a construction progress measurement system for each contractor and compile/convert with overall schedule. (PMS).
Forecasting and address the conflict between construction contractors.
Compiling sub-contractors data and prepare Daily, Weekly and Monthly reports.
Taking the physical progress and compare with the sub-contractors reports and Updating progress in P6 (Level IV).
Preparing weekly key performance index report (KPI).
Preparing and auditing Quantity Man-hours Report (QMR).
Preparing and Maintaining a construction progress measurement system for each contractor and compile/convert with overall schedule. (PMS).
Forecasting and address the conflict between construction contractors.