Norway (EU.NO)

Lead planner / Planning Manager, Aker Solutions, Valhall Wellhead Control System Upgrade

START Date: 
April, 2008
END Date: 
December, 2010

Employer: Aker Elektro AS
Project: Valhall
Project Size: 100 - 200 mill.
Country: Norway
Position: Planning Manager
Client: BP Norge AS
Working as senior EI&T planer in Valhall Wellhead Control System Upgrade with multidiscipline responsibilities.
Responsibilities:
- Establish and maintain construction schedules.
- Develop, maintain and promote master plan, discipline / multi-discipline.
- Develop summation levels
- Develop, maintain and promote the project's master plan, discipline / multi-discipline.
- Follow up the progress report

Gunnar Næss

First Name: 
Gunnar
Last Name: 
Næss
Oldest experience: 
Jun 1983 (41.3 yrs experience, WARNING: 13.4 years variance with Professional Since)
Years Experience: 
41

Lead planner / Planning Manager /Project Manager, ICTEC , Telenor Norway, BRAIN ( BRoadband All Ip Network)

START Date: 
June, 1983

Project Management Experience since 1990 with speciality in Planning. Earlier Experience from data-programming and Unix System Programming. Participated in major ICT projects in Norway since 2000 both internal Telenor and external  projects as ICT sub-contractor to new hospitals in Norway ( St.Olavs hospital and Nye AHUS hospital)

Gustavo Cordoba

First Name: 
Gustavo
Last Name: 
Cordoba

Project Planning & Control Specialist with extensive experience in Oil & Gas (Upstream /Downstream, Off/Onshore), Power, and Industrial Process Plants Projects.

Professional Since: 
Dec-1987 (36.8 yrs experience)
Oldest experience: 
Oct 2007 (17.0 yrs experience, WARNING: 19.8 years variance with Professional Since)
Years Experience: 
3

Erskine Rozario

First Name: 
Erskine
Last Name: 
Rozario
Professional Since: 
Nov-2005 (18.9 yrs experience)
Years Experience: 
0

Senior Project Engineer, Acergy Norway AS, Stavanger, Norway, Langeled Pipeline - 1166 km, 44"och 42" pipelines from Ormen Lange Norge till Easington, UK.

START Date: 
June, 2006
END Date: 
February, 2008

 

  • Working within the Rigid Pipeline section, and responsible for assisting sub-sea pipeline related projects, tenders and studies.
  • Review Client's technical documentation and requirements during the bid phase and ensure an adequate standard of technical documentation are prepared.
  • Perform and/or supervise the correct execution of sea-line design and installat

Maryanne MacRae

First Name: 
Maryanne
Last Name: 
MacRae
Professional Since: 
Jan-1982 (42.6 yrs experience)
Oldest experience: 
Jul 2009 (15.2 yrs experience, WARNING: 27.5 years variance with Professional Since)
Years Experience: 
1

Paul Angell

First Name: 
Paul
Last Name: 
Angell
Professional Since: 
Jul-2005 (19.1 yrs experience)
Oldest experience: 
Sep 2008 (16.0 yrs experience, WARNING: 3.1 years variance with Professional Since)
Years Experience: 
1

Olaf Denris

First Name: 
Olaf
Last Name: 
Denris
Professional Since: 
Jul-2002 (22.1 yrs experience)
Oldest experience: 
Sep 2008 (16.0 yrs experience, WARNING: 6.1 years variance with Professional Since)
Years Experience: 
2

ian meister

First Name: 
ian
Last Name: 
meister
Professional Since: 
Oct-2007 (16.9 yrs experience)
Oldest experience: 
Aug 2008 (16.1 yrs experience, WARNING: 0.8 years variance with Professional Since)