Develop overall schedules, develop work schedules, track and progress each phase of project, AMEC Paragon, Various BP Offshore Platforms

START Date: 
November, 2008
END Date: 
February, 2011

Sr. Planner/Scheduler

Develop schedules for FEED phase, and conduct schedule and cost risk analysis.

Lead/Senior Planning Engineer, BP, Various BP Offshore Platforms

START Date: 
September, 2008
END Date: 
July, 2010

Planning Engineer for the Offshore SNS gas platforms. Lad for the system integration of P6 and Maximo.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
500