Lead Project Planner, Mitsui Babcock, Total Lindsey Oil Refinery, Stage 3/4 T & I HFA Shutdown

START Date: 
March, 2005
END Date: 
August, 2005
  • Prepare resourced shutdown programme from client SAP generated work orders (WO).
  • Update & maintain WO database and all associated WO documentation.
  • Produce progress ā€˜S’ curves and resource histograms.
  • To liaise with client on all aspects of work pack development and approval.