Residential Houses

Civil Site Engineer, AL Habeeb Contracting , Residential Houses

START Date: 
August, 2001
END Date: 
March, 2003

Key Deliverables:

ð  Ensuring site operations are executed as per approved shop drawings.

ð  Arranged materials from local vendors, recorded contractor work progress & manpower.

Settled the payments on weekly & monthly basis.

Estimator, PT. Anugerah Citra abadi, Residential Houses

START Date: 
May, 2005
END Date: 
July, 2006

Key Role               :          

ü  Estimate volume of work.

ü  Making Baseline Budget of Project

ü  Submitting the items and quantity of material which needed on the project to the Supervisor.

ü  Prepare the Bid Document.

ü  Control the use of Material which needed.

ü  Updating material price for Monthly Unit Price

PLANNER, LOCAL RESIDENTIAL HOUSES, RESIDENTIAL HOUSES

START Date: 
July, 2013

Professional Experience:

 

Planning Engr / Civil Engineer, Residential Houses at Nabua , Camarines Sur, Philippines-  January 2012 to Present.

 

, Site Engineer, project supervision among workers to meet the target accomplishment in site, conduct site inspection, involves in structural and architectural works.

, Study, review and revised design drawings based on Specifications as per resident consultant engineer approval.

PLANNER, LOCAL RESIDENTIAL HOUSES, RESIDENTIAL HOUSES

START Date: 
July, 2013

Professional Experience:

 

Planning Engr / Civil Engineer, Residential Houses at Nabua , Camarines Sur, Philippines-  January 2012 to Present.

 

, Site Engineer, project supervision among workers to meet the target accomplishment in site, conduct site inspection, involves in structural and architectural works.

, Study, review and revised design drawings based on Specifications as per resident consultant engineer approval.

Project Engineer, C S L Construction Corporation, Manila, Philippines, Roads and Drainage, Residential Houses, Warehouses, School buildings

START Date: 
September, 1993
END Date: 
December, 1996

 

  • Prepare the overall activity schedule, labor and material schedule.
  • Prepare project cash flow and s-curve.
  • Manage the general coordination of work on site.
  • Review and participate in preparation of variation order requests, and implement accepted variation orders with regards to schedule, manpow