Impala 20 Shaft

Lead Project Planner, TWP Projects, Impala 20 Shaft

START Date: 
August, 2007

Impala Platinum No. 20 Shaft (RSA)- Full E.P.C.M. Project [Involvement: August 2007 to Present]

I was involved in all the planning of this project: compromising of the Surface common and complex infrastructure works as well as the Normal sinking of two shafts (Main and Ventilation). All development (Incline and Decline), all underground construction works as well as the changeover to an operational mine. (Reef has been hoisted from both dips).